2015 Bond Information » Project Progress

Project Progress

Update 04/19/2016
 
The crews have been busy at work, finishing up the Ag facility, progressing on the Primary addition and finalizing plans for the JH & HS renovations. The Architectural team has completed plans for the new elementary campus and we are set to break ground the week of 04/25/2016!!!! The construction team will be working diligently to have the elementary campus open for the 2017-2018 school year.
 
We are just short of a year since the voters passed a 63 million bond election to improve our school and we are happy to announce that we are complete with our first build. The keys to the Ag facility are set to be turned over form Joeris General Contractors to Pleasanton ISD, by the end of the month.
 
Demo has begun at both the JH & HS campus this week, JH will receive new flooring, lighting, wall finish, library and courtyard area! The HS will also receive the new flooring, lighting, wall finish, library, along with a new culinary arts, welding shop, and horticulture classrooms. A new concession stand at the stadium is also in the works.
 
 
Update 2/29/2016
 
The new elementary campus is set to bid on the 10th of March!
 
Update 1/25/2016
Plans for the JH and HS renovations are complete and will be released to Joeris to begin the bidding process. The JH & HS renovations are expected to begin as soon as school is out for the summer. Elementary plans are tracking completion towards the 2nd week in February and will be released for bidding soon thereafter.
 
 
Subcontractors interested in bidding, should contact Tom Lyons @ Joeris General Contractors for more information
Office: 210-494-1638  Ext: 1385
Fax: 210-494-1639
 
 
Update  01/08/2016
Erection of both the Ag Facility, and Primary addition are well underway. Plans and drawings for the HS, JH & PIC renovations are nearing the final stages along with surveys and plans for the brand new elementary campus. Bidding for the renovation and new elementary campus will occur over the next few months.
 
Office: 210-494-1638  Ext: 1385
Fax: 210-494-1639
 
Update 12/08/2015
The concrete slab has been poured at the Primary campus. Concrete contractors started in the early morning hours to ensure a successful pour. The finished result is a beautiful slab ready for steel erection over the winter holiday!
 
Update 11/20/2015
Concrete slab was poured at the Ag Facility site.
 
Update: 10/16/2015
Schematic drawings for the New Elementary were approved by the Board of Trustees on 10/13/2015. Look for architectural renderings to be uploaded soon! 
 
Update: 09/29/2015
 
Visible progress has started, as apparent by the new Joeris job site trailer placed on PISD property last Friday. This temporary facility will be hub for Construction Managers over the next few years as the 2015 Bond Program comes to fruition.

Although this jobsite trailer is the first visible sign of progress, Architects, Estimators, Construction Managers, District Staff and School Board Trustees have been hard at work, designing, planning and coordinating all of the projects set forth in the 2015 Bond program.

The first projects to break ground will be an addition to the Primary campus and new construction of an Agricultural facility. The Primary addition will add 8 classrooms, 24 restrooms and remodel of the current restroom entrances. Construction of the Agricultural facility will be a welcome addition to the district. This 15,000 sf facility will include animal pins, show arena, and feed storage.